| THE SUBDIVISION ORDINANCE ACCESSIBLE ON THIS SITE IS A DRAFT VERSION AND IS CURRENTLY UNDER REVISION. The Plan Commission will review the Subdivision Ordinance through public hearings. Upon final review of each document, the Plan Commission will make a recommendation to the City Council for final approval regarding the proposed changes. Please contact Building and Zoning Official Mike Sutfin or City Planner Tami Huftel at 815-433-0161 with any questions regarding subdivision issues. __________ * Cross References: Any ordinance dedicating or accepting any plat or subdivision in the city, or providing regulations for the subdivision of land saved from repeal, § 1-16(10); buildings and building regulations, ch. 22; manufactured homes and trailers, ch. 58; planning, ch. 74; streets, sidewalks and other public places, ch. 86. State Law References: Subdivision powers, 65 ILCS 5/11-12-5(1)(a);
Plat Act, 765 ILCS 205/0.01 et seq.
ARTICLE VII - GUARANTEE OF PERFORMANCE
A final plat shall not be released by the City unless the following supporting documents and fees have been submitted to the City. Sec. 90-7.1 PLANS, REPORTS AND STUDIES
A form of security in a form acceptable to the City. If an irrevocable letter of credit is furnished, it shall be in substantially the following form:
The below stated procedures shall be followed for: Sec. 90-7.2-B. Initialization of Security Amounts 1. Three (3) sets of full and final calculations for establishment of security amount shall be submitted to the City Engineer no less that ten (10) working days prior to Council consideration of the Final Plat. 2. Calculations shall be in bid format, and shall show individual items, quantities, unit prices, extensions, and total of Phase I and Phase II and Phase III improvements. See subdivision standards 1200 A - 1200 F. 3. Subdivision security shall be 125% of the value of improvements. 4. No more than three (3) Letters of Credit (Phase I, Phase PHASE I - IMPROVEMENTS - Erosion Control PHASE II - IMPROVEMENTS - Curb and Gutter PHASE III -IMPROVEMENTS - Bikepaths Sec. 90-7.C REDUCTION OF SECURITY AMOUNTS 1. Reductions can be made only after an entire phase is completed. 2. Reductions shall be submitted to the City Engineer no less than sixty (60) working days prior to Council consideration of the reduction. Reductions requested during the winter season may be delayed for Council consideration if the punchlist cannot be completed. 3. Periodic reduction requests shall be accompanied by an itemized listing of completed and uncompleted work in the same format as Sec. 90-7.2-B. Requests made for Phase I improvements shall be accompanied by the following documents which shall be submitted to the City Engineer: - Video tapes and logs of all sanitary sewer lines. 4. Requests made for Phase 2 improvements shall be accompanied by the
following documents which shall be submitted to the City Engineer: 5. Punch lists of noted deficiencies shall be submitted to the Applicant, no more than thirty (30) working days following receipt of the request for reduction. 6. Repairs required by the punchlist shall be completed by the Applicant, and witnessed by the City no less than ten (10) working days prior to Council consideration. 7. Final recommendation of acceptance or declination of acceptance shall be submitted to the Applicant, no less than eight (8) working days prior to Council consideration of the acceptance. 8. All reduced security amounts shall be calculated as follows: 9. No letter of credit shall be reduced to less than 10% of initial value or $25,000, whichever is greater before the completed improvements are accepted by the City of Ottawa. 10. No letter of credit shall be reduced prior to the submittal of as-built drawings Sec. 90-7.2-D ACCEPTANCE OF PUBLIC IMPROVEMENTS 1. Application for acceptance of public improvements shall be submitted to the City Engineer no less than ninety (90) working days prior to Council consideration of the acceptance. Acceptance during the winter season may be delayed for Council consideration if the punchlist can not be completed. 2. Punch lists of noted deficiencies shall be submitted by the City Engineer and to the Applicant no less than thirty (30) working days prior to Council consideration of the acceptance. 3. Repairs required by the punchlist shall be completed by the Applicant, and witnessed by the City no less than ten (10) working days prior to Council consideration. 4. Final recommendation of acceptance or declination of acceptance shall be submitted by the City Engineer and to the Applicant no less than eight (8) working days prior to Council consideration of the acceptance. Sec. 90-7.2-E EXPIRATION OF SECURITY 1. Security shall not expire without ninety (90) working days prior notification by the Applicant or Surety, nor without written City approval of the expiration. 2. The City Engineer shall review the work and submit a punch list if necessary to the Applicant prior to the scheduled expiration date. 3. Repairs required by the punchlist shall be completed by the Applicant, and witnessed by the City no less than ten (10) working days prior to Council consideration. 4. Final recommendation of acceptance or declination of acceptance shall be submitted by the City Engineer to the Applicant no less than eight (8) working days prior to Council consideration of the acceptance. Sec. 90-7.3 OTHER REQUIREMENTS A. Plats of dedication; or easements if required. B. Sewer and Water connection fees. C. IEPA, IDOT, LCHD, ICCHD permits if required. D. All recapture fees if required. E. Any and all fees required by annexation agreement, City ordinances,